Ethelton | Tormore | Domett | ||||||||||||||||||||||
Ethelton--Tormore | Tormore--Domett | |||||||||||||||||||||||
5.4km | 8.1km |
Go to Tormore on the Network Diagram
Tormore | Westlands | Benmore | - | 25/5/1969 | Station building and platform, goods shed, loading bank, and cattle and sheep yards. | Cheviot Branch | - | W 3337 | WRD | Canterbury | S | 61081 |
Tormore | - | - | - | 17/7/1906 | Tormore station – providing postmistress with cottage. | Waipara – Cheviot Railway | - | W 3 | PWD | Canterbury | S | 61082 |
Tormore | - | - | - | 13/9/1906 | Completion of line to Tormore. | Waipara – Cheviot Railway | - | W 3 | PWD | Canterbury | S | 61083 |
Tormore | - | - | - | 12/10/1906 | Hire of railway wagons carrying private goods n extension to Tormore. | Waipara – Cheviot Railway | - | W 3 | PWD | Canterbury | S | 61084 |
Tormore | - | - | - | 27/10/1906 | Tormore Section – Certificate of Inspection. | Waipara – Cheviot Railway | - | W 3 | PWD | Canterbury | S | 61085 |
Tormore | - | - | - | 14/11/1906 | The Ethleton – Tormore Section opened, 5 miles 28 chains in length. | Waipara – Cheviot Railway | - | W1, 12/1 | PWD | Canterbury | S | 61086 |
Tormore | - | - | - | 14/12/1906 | Accommodation station building, passenger platform, goods shed 30ft x 20ft, loading bank, cattle yards, coal shed, urinals. | Waipara – Cheviot Railway | - | W 3337 | WRD | Canterbury | S | 61087 |
Tormore | - | - | - | 14/12/1906 | Flag station opened, 26 miles 24 chains from Waipara. | Waipara – Cheviot Railway | - | W 3337 | WRD | Canterbury | S | 61088 |
Tormore | - | - | - | 14/12/1906 | Loop 58 wagons, loop 12 wagons, backshunt 12 wagons (coal shed), backshunt 18 wagons (north). | Waipara – Cheviot Railway | - | W 3337 | WRD | Canterbury | S | 61089 |
Tormore | - | - | - | 24/9/1907 | Tormore – Domett Section – stating line was handed over in an incomplete state and considerable expenditure incurred. | Waipara – Cheviot Railway | - | W 3 | PWD | Canterbury | S | 61090 |
Tormore | - | - | - | 18/10/1907 | Fencing platelayers' cottages. | Waipara – Cheviot Railway | - | W 3 | PWD | Canterbury | S | 61091 |
Tormore | - | - | - | 25/12/1922 | Damage caused by earthquake in vicinity of station. | Waipara – Cheviot Railway | - | W3734/38 | WRD | Canterbury | S | 61092 |
Tormore | - | - | - | 31/7/1941 | Installation of ground frame levers in hand. | Waipara – Cheviot Railway | - | W3180, Pub3/10 | WRD | Canterbury | S | 61093 |
Tormore | - | - | - | 2/10/1960 | Mileage 66 miles 68 chains from Christchurch. | Waipara – Cheviot Railway | - | W 3337 | WRD | Canterbury | S | 61094 |
Tormore | - | - | - | 10/4/1978 | Station building, siding, and loading bank. | Waipara – Cheviot Railway | - | W2559, 505/4/2 | WRD | Canterbury | S | 61095 |
Tormore | - | - | - | 3/8/1978 | To close for all traffic from 6/8/1978. Loop to be retained for crossing purposes. | Waipara – Cheviot Railway | - | W 2493, 98/841/1 | WRD | Canterbury | S | 61096 |
Tormore | - | - | - | 2/11/1987 | Main North Line – 105.27km from Addington (0.00km). | Waipara – Cheviot Railway | - | W 3337 | WRD | Canterbury | S | 61097 |
Tormore | - | - | - | 25/11/1988 | Still used for timetabled running of trains. | Waipara – Cheviot Railway | - | W 3337 | WRD | Canterbury | S | 61098 |