File Records:Landing

From Railway Knowledge Base for New Zealand
Jump to navigation Jump to search
Rotokohu Landing Oweka
Trail StnSL.png Trail SectR.png Trail StnL.png Trail SectR.png Trail StnSR.png
Rotokohu--Landing Landing--Oweka
5.9km 4.7km

Go to Landing on the Network Diagram



Name Alt 1 Alt 2 Alt 3 Date Details Railway Rly 2 Reference Source Locality Island Sequence
Landing Inangahua Landing - - 14/7/1902 Advisability of constructing a combined rail and road bridge over the Inangahua River at the Landing. Reefton – Inangahua Railway - W 3 PWD Westland S 25383
Landing Inangahua Landing - - 31/12/1909 Proposed flag station near Inangahua Landing at 50 miles 70 chains. Reefton – Inangahua Railway - W 3 PWD Westland S 25384
Landing Inangahua Landing - - 2/1910 Sleepers – has just enough to complete to the Landing. Reefton – Inangahua Railway - W 3 PWD Westland S 25385
Landing Inangahua Landing - - 2/3/1911 Cronadun – Landing Section – forwarding estimate to complete. Reefton – Inangahua Railway - W 3 PWD Westland S 25386
Landing Inangahua Landing - - 21/3/1911 Landing station buildings – estimate £1,600. Reefton – Inangahua Railway - W 3 PWD Westland S 25387
Landing Inangahua Landing - - 7/6/1911 Station buildings – schedule of tenders. Reefton – Inangahua Railway - W 3 PWD Westland S 25388
Landing Inangahua Landing - - 15/6/1911 Station buildings – contract let to Walter Kemp, Reefton, amount £1575.7.0. Reefton – Inangahua Railway - W 34/1 PWD Westland S 25389
Landing Inangahua Landing - - 26/6/1911 Station buildings – contract signed. Reefton – Inangahua Railway - W 3 PWD Westland S 25390
Landing Inangahua Landing - - 4/8/1911 Conveyance of material between Cronadun and the Landing. Reefton – Inangahua Railway - W 3 PWD Westland S 25391
Landing Inangahua Landing - - 16/11/1911 Inangahua Landing station buildings – extras to contract – requesting authority £22.16.0. Reefton – Inangahua Railway - W 3 PWD Westland S 25392
Landing Inangahua Landing - - 15/12/1911 Above contract completed. Reefton – Inangahua Railway - W 34/1 PWD Westland S 25393
Landing Inangahua Landing - - 24/2/1912 Walter Kemp's contract for station buildings completed. Reefton – Inangahua Railway - W 12 PWD Westland S 25394
Landing Inangahua Landing - - 8/11/1912 Maintenance of completed line from Cronadun to Landing. Reefton – Inangahua Railway - W 3 PWD Westland S 25395
Landing Inangahua Landing - - 11/9/1913 Ballasting line from Cronadun to Landing – requesting authority £1,000. Reefton – Inangahua Railway - W 3 PWD Westland S 25396
Landing Inangahua Landing - - 24/12/1913 Approval to remove portion of the No 1 loop. Reefton – Inangahua Railway - W2278, 05/525 WRD Westland S 25397
Landing Inangahua Landing - - 1/7/1914 Accommodation station building, passenger platform (left side), cart approach to platform, goods shed 20ft x 30ft, loading bank, engine shed, water service. Reefton – Inangahua Railway - W 3337 WRD Westland S 25398
Landing Inangahua Landing - - 1/7/1914 Flag station opened 52 miles 23 chains from Stillwater. Reefton – Inangahua Railway - W 3337 WRD Westland S 25399
Landing Inangahua Landing - - 1/7/1914 Loop 28 wagons, loop 28 wagons, backshunt 8 wagons (engine shed). Reefton – Inangahua Railway - W 3337 WRD Westland S 25400
Landing Inangahua Landing - - 22/8/1918 Engine shed at the Landing , on the Buller Gorge Railway. This engine shed was erected some years ago now and is never used, nor likely to be. It is 65 feet by 20 feet. Reefton – Inangahua Railway - W 2381, 16/1800/1 WRD Westland S 25401
Landing Inangahua Landing - - 24/10/1941 Crossing loop lifted. Reefton – Inangahua Railway - W2559, 505/4/2 WRD Westland S 25402
Landing Inangahua Landing - - 23/5/1949 Backshunt to be removed. Reefton – Inangahua Railway - W2559, 505/4/2 WRD Westland S 25403
Landing Inangahua Landing - - 2/10/1960 Mileage 32 miles 27 chains from Westport. Reefton – Inangahua Railway - W 3337 WRD Westland S 25404
Landing Inangahua Landing - - 27/4/1980 Closed to all traffic. Reefton – Inangahua Railway - 00/2107/1 NZRLS Westland S 25405