Latest revision as of 08:25, 24 February 2022
Kawatiri | Gowan Bridge | ||||||||||||
Kawatiri--Gowan_Bridge | |||||||||||||
{{{Prev_Dist}}} |
Go to Gowan Bridge on the Network Diagram
Name | Alt 1 | Alt 2 | Alt 3 | Date | Details | Railway | Rly 2 | Reference | Source | Locality | Island | Sequence |
Gowan Bridge | - | - | - | 6/1926 | Platelayers' cottages. Tender of W Baston accepted, amount £1152.10.0. | Nelson Section | - | W 34/2 | PWD | Nelson | S | 15181 |
Gowan Bridge | - | - | - | 4/1928 | Goods shed. Tender of Robertson Brothers Ltd accepted, amount £775.17.6. | Nelson Section | - | W 34/3 | PWD | Nelson | S | 15182 |
Gowan Bridge | - | - | - | 5/1928 | Station buildings. Tender of Robertson Brothers Ltd accepted, amount £758.17.2. | Nelson Section | - | W 34/3 | PWD | Nelson | S | 15183 |
Gowan Bridge | - | - | - | 25/10/1928 | Engine F 146, at Nelson, is to be hired to the Public Works Department for use on the Kawatiri Gowan Bridge Section. | Nelson Section | - | W2278, 03/3844 | WRD | Nelson | S | 15184 |
Gowan Bridge | - | - | - | 13/5/1929 | Material for the Public Works Department being carried from Kawatiri to Gowan Bridge. | Nelson Section | - | W2278, 03/3844 | WRD | Nelson | S | 15185 |
Gowan Bridge | - | - | - | 10/4/1930 | Sheep traffic is being worked between Kawatiri and Gowan Bridge. | Nelson Section | - | R-W1, 22/146 | WRD | Nelson | S | 15186 |
Gowan Bridge | - | - | - | 7/8/1930 | Line to Gowan Bridge nearly completed. | Nelson Section | - | W4098, 04/1739/1 | WRD | Nelson | S | 15187 |
Gowan Bridge | - | - | - | 29/5/1931 | Construction beyond Gowan Bridge abandoned. | Nelson Section | - | W2278, 03/3844 | WRD | Nelson | S | 15188 |
Gowan Bridge | - | - | - | 25/6/1931 | The last of the Public Works Department rails will be lifted next week. | Nelson Section | - | JRS/337 | ATL | Nelson | S | 15189 |
Gowan Bridge | - | - | - | 22/9/1932 | Matters have been finalised with the Public Works Department re: conveying sleepers from Gowan Bridge to Glenhope. Section is certified to be in a fit condition for traffic. | Nelson Section | - | JRS/337 | ATL | Nelson | S | 15190 |
Gowan Bridge | - | - | - | 3/10/1932 | The transfer of sleepers (purchased by the Railway Department) from Gowan Bridge to Nelson has been completed. | Nelson Section | - | W2278, 03/3844 | WRD | Nelson | S | 15191 |
Gowan Bridge | - | - | - | 9/11/1932 | Conveyance of sleepers was completed on 3/10/1932. | Nelson Section | - | JRS/337 | ATL | Nelson | S | 15192 |
Gowan Bridge | - | - | - | 26/3/1933 | Transport of rails from Gowan Bridge for the Public Works Department was completed on Saturday, 24th instant. | Nelson Section | - | JRS/337 | ATL | Nelson | S | 15193 |
Gowan Bridge | - | - | - | 24/6/1933 | The transport of 249 rails from Gowan Bridge has been completed. These rails are being transferred to Ohura by the Public Works Department. | Nelson Section | - | W2278, 03/3844 | WRD | Nelson | S | 15194 |
Gowan Bridge | - | - | - | 22/5/1950 | The Railway Department controls the line between Nelson and Kawatiri and the Ministry of Works the line beyond Kawatiri to Gowan Bridge. | Nelson Section | - | W2559, 505/4/2 | WRD | Nelson | S | 15195 |
Gowan Bridge | - | - | - | 22/5/1950 | Discarded rails at Gowan Bridge – these are light weight rails formerly used in service sidings and are not suitable for laying on the permanent way. | Nelson Section | - | W2559, 505/4/2 | WRD | Nelson | S | 15196 |
Gowan Bridge | - | - | - | 20/8/1952 | Goods shed 40ft x 20ft (with 12 foot verandah). | Nelson Section | - | R3, 28/1870 | WRD | Nelson | S | 15197 |
Gowan Bridge | - | - | - | 20/8/1952 | The goods shed is built of timber framing and corrugated iron and is in good condition. | Nelson Section | - | R3, 28/1870 | WRD | Nelson | S | 15198 |
Gowan Bridge | - | - | - | 22/91932 | Engine FA 374, at present idle at Glenhope, used to bring out the sleepers from Gowan Bridge. | Nelson Section | - | W2278, 03/3844 | WRD | Nelson | S | 15199 |