File Records:Hundalee: Difference between revisions

From Railway Knowledge Base for New Zealand
Jump to navigation Jump to search
(Initial Data Input)
No edit summary
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
{{Trail_Station|Prev_Station=[[Parnassus]]|Next_Station=[[Claverley]]|Prev_Section=[[Parnassus - Hundalee]]|Next_Section=[[Hundalee - Claverley]]}}
{{Trail_Station|Prev_Station=[[Ferniehurst]]|Next_Station=[[Claverley]]|Prev_Section=[[Ferniehurst--Hundalee]]|Next_Section=[[Hundalee--Claverley]]|Prev_Dist=8.8km|Next_Dist=5.7km}}
[[South_Island_Network_Diagram#{{PAGENAME}} | Go to  {{PAGENAME}} on the Network Diagram]]
[[South_Island_Network_Diagram#{{PAGENAME}} | Go to  {{PAGENAME}} on the Network Diagram]]



Latest revision as of 19:17, 31 January 2022

Ferniehurst Hundalee Claverley
Trail StnSL.png Trail SectR.png Trail StnL.png Trail SectR.png Trail StnSR.png
Ferniehurst--Hundalee Hundalee--Claverley
8.8km 5.7km

Go to Hundalee on the Network Diagram



Hundalee - - - 1/4/1936 Buildings, etc., required at Hundalee: approach road, 2 No points and crossings (1 in 9), shelter shed and ladies waiting room (PWD 56529), platform, 200ft (PWD 24118, concrete), latrines (2 stall), goods shed (30ft x 20ft with verandah), loading bank (PWD 24118, concrete, 27ft x 15ft), sheep and cattle yards (PWD 24816, double yards), water supply, 2 No stop blocks, platform fences, 2 No platelayers' cottages. Waipara – Blenheim Railway - W1, 12/1 PWD Marlborough S 19618
Hundalee - - - 11/10/1937 Hundalee station arrangement approved. Waipara – Blenheim Railway - W1, 12/71 PWD Marlborough S 19619
Hundalee - - - 27/9/1938 Buildings required at Hundalee: station building (62ft x 13ft, PWD Drawing 8851, with stationmaster's office extended 8ft), goods shed (35ft x 20ft), three staff cottages. Waipara – Blenheim Railway - W1, 12/71 PWD Marlborough S 19620
Hundalee - - - 10/1939 Ferniehurst, Hundalee, and Claverley stations – erection of 7 cottages – tender of D Hall accepted, amount £6300.0.0. Waipara – Blenheim Railway - W 34/1 PWD Canterbury S 19621
Hundalee - - - 10/1939 Station buildings – no tenders received. Waipara – Blenheim Railway - W 34/1 PWD Canterbury S 19622
Hundalee - - - 27/11/1939 Accommodation shelter shed, passenger platform (left side of line, goods shed 30ft x 20ft, loading bank, cattle and sheep yards. Waipara – Blenheim Railway - 00/2107/1 NZRLS Canterbury S 19623
Hundalee - - - 27/11/1939 First goods train to Hundalee. Waipara – Blenheim Railway - W3180, Pub 1/3 WRD Marlborough S 19624
Hundalee - - - 27/11/1939 Loop 62 wagons, loop 27 wagons, loop 27 wagons, backshunt 15 wagons (cattle yards). Waipara – Blenheim Railway - 00/2107/1 NZRLS Canterbury S 19625
Hundalee - - - 27/11/1939 Parnassus to Hundalee Section handed over to Working Railways Department. Hundalee station opened, 94 miles 51 chains from Addington. Waipara – Blenheim Railway - 00/2107/1 NZRLS Canterbury S 19626
Hundalee - - - 27/11/1939 Parnassus to Hundalee Section opened for goods traffic, length 11 miles 60 chains. Waipara – Blenheim Railway - W1, 12/1 PWD Canterbury S 19627
Hundalee - - - 27/11/1939 Work completed on new line between Parnassus and Hundalee. Waipara – Blenheim Railway - W3180, Pub 3 WRD Canterbury S 19628
Hundalee - - - 11/12/1939 First passenger train to Hundalee. Waipara – Blenheim Railway - W3180, Pub 1/3 WRD Marlborough S 19629
Hundalee - - - 11/12/1939 Parnassus to Hundalee Section opened for passenger traffic. Waipara – Blenheim Railway - W1, 12/1 PWD Canterbury S 19630
Hundalee - - - 14/12/1939 Requesting authority £120 for furnishing Hundalee station. Waipara – Blenheim Railway - W1, 12/71 PWD Marlborough S 19631
Hundalee - - - 21/8/1940 Hundalee is the present terminus of the southern section. Waipara – Blenheim Railway - W1, 12/71 PWD Marlborough S 19632
Hundalee - - - 1/8/1941 Parnassus to Hundalee Section handed over to Railways Department. Waipara – Blenheim Railway - W1, 12/1 PWD Canterbury S 19633
Hundalee - - - 1/4/1942 Post Office operated by Railways Department staff opened. Waipara – Blenheim Railway - Mails by Rail in NZ R Startup Canterbury S 19634
Hundalee - - - 24/6/1942 Three permanent cottages have been completed. Waipara – Blenheim Railway - W1, 12/71 PWD Marlborough S 19635
Hundalee - - - 8/7/1943 The line between Oaro and Hundalee will be open for traffic on Thursday 8th instant. Waipara – Blenheim Railway - W1, 12/71 PWD Marlborough S 19636
Hundalee - - - 14/7/1943 The line between Oaro and Hundalee has been closed because of slips. Waipara – Blenheim Railway - W1, 12/71 PWD Marlborough S 19637
Hundalee - - - 3/7/1944 Post Office removed from station. Waipara – Blenheim Railway - Mails by Rail in NZ R Startup Canterbury S 19638
Hundalee - - - 13/12/1945 On Saturday, 15/12/1945, the Hundalee – Kaikoura Section of the South Island Main Trunk Railway will be taken over by the Working Railways Department. Waipara – Blenheim Railway - W 2903 WRD Marlborough S 19639
Hundalee - - - 17/12/1945 Work completed on new line between Hundalee and Kaikoura. Waipara – Blenheim Railway - W3180, Pub 3 WRD Canterbury S 19640
Hundalee - - - 29/7/1948 Name approved for Public Works Department in 1939. North bank of Conway River. Waipara – Blenheim Railway - W3199, 00/2107/1 WRD Canterbury S 19641
Hundalee - - - 2/10/1960 Mileage 96 miles 5 chains from Christchurch. Waipara – Blenheim Railway - W 3337 WRD Marlborough S 19642
Hundalee - - - 29/3/1981 Closed to all traffic. Waipara – Blenheim Railway - W 3337 WRD Marlborough S 19643
Hundalee - - - 15/3/1984 Closed for all traffic. Waipara – Blenheim Railway - 00/2107/1 NZRLS Canterbury S 19644